Insights · November 18, 2026

Moving off SSIS without losing the numbers


The risky move is not staying on SSIS. It is turning a package off before the new pipeline has matched it.

SSIS estates get modernized in speeches and big-bang projects. The speeches are cheap. The big-bang is how a close gets missed. A calmer path is dull on purpose: one workload, a parallel run, a written comparison, then a cutover.

Keep the old job on the schedule

The legacy package stays until the person who owns the number signs the comparison. Until that signature, the new pipeline is a candidate, not the system of record. Rollback is the old schedule you never disabled.

Compare grain, keys, and totals

Row counts are not enough if the grain changed. Totals are not enough if a filter moved. Write the grain, the business key, and the totals that matter, and diff them for an agreed set of days. Record every gap, including the ones you intend to keep because the old number was wrong.

Make schema change loud

A new column is rarely the incident. A renamed column that maps to the wrong field, and a report that still renders, is the incident. The pipeline should fail when the shape drifts from the contract, not publish a quieter wrong total.

Change the model on purpose

If the semantic model and the upstream job change in the same weekend, you will not know which one moved the number. Prefer to keep the certified model stable while the pipeline is proven, or change them as a planned pair with the comparison still in place.

Leave an owner

A Fabric pipeline with no named owner is the same risk as the SSIS package only one person understood. The handover is part of the slice: who reruns it, who gets the alert, and where the notes live.

If you want this done against a real package, start with the readiness assessment or a single-question proof of concept.